Client: PREdistribude, a.s. Completion: 2020 The project addresses the rehabilitation of damaged structures of the existing underground technological shaft K15 KT Pražačka and Š12 KT Žižkov, […]
Client: PREdistribuce, a.s. Completion: 2021 New construction which will be used to lead 110 kV and 22 kV cables from the TR Karlín substation to the […]
Client: ČSAD Praha holding a.s. Completion: 2020 The subject of construction works is relocation of the Hradní sewer and the subsequent relocation of connections or other […]
Client: Statutory City Brno Completion: 2018 As part of the reconstruction, the old water lines from 1951 will be replaced by a new pipeline of the same […]
Client: Capital city Prague Completion: 2015 Building of a sewerage by a trenchless technology – tunnelling method, profile LB3, excavated place underground 3,5m², total length of […]
Client: PREdistribuce, a.s. Completion 2014 In the premises of the substation there are 2 branches of cable channels with lengths of 71.6 m and 72.5 m […]
Client: PREdistribuce, a.s. Completion 2012 This project concerns the Bohdalec tunnel extension, which is designed for cables of 110 kV and 22 kV. The vertical alignment […]
Client: Zoologická a botanická zahrada města Plzně, příspěvková organizace Completion 2012 The task is the complete reconstruction of the existing underground space of a mined adit […]
Client: NAVATYP a.s. Completion 2008 The construction represents part of a strategic energy interconnection between the 110/22 kV Karlov and the 110/22 kV Smíchov substations, based […]