Client: Povodí Odry, státní podnik

Completion: 2018


Realization of a dry retention reservoir in order to reduce flood flows and flow of sediment and to protect the Karlovice municipality from the negative effects of floods caused by torrential rainfall.
The construction consists mainly of landscaping, construction of a 16m high non-homogeneous dam with an injecting screen, an associated building, a waste channel, a service road, an emergency spillway, revitalization treatments in the floodplain and around the tank. Part of the building is also the relocation of the II class class.